Getting a building permit in Los Angeles

The order of a Los Angeles permit through LADBS: check zoning, apply online, plan check, fees, then inspections until the final sign-off.

Construction in the city of Los Angeles runs through the Los Angeles Department of Building and Safety, known as LADBS. It reviews plans, issues permits, inspects work and enforces the building codes. Zoning, meaning what a parcel may be used for and how big a building can be, is decided by City Planning, a different department. A project usually needs both. The process has a predictable order, and knowing it saves weeks.

When you need a permit

As a general rule, you need a permit to build, add to, alter, demolish or change the use of a building, and for work on electrical, plumbing and mechanical systems. Common examples are a room addition, a new bathroom, a re-roof of a certain size, a water heater replacement, a retaining wall above a certain height and a swimming pool. Some small items, such as painting, flooring and replacing a faucet, do not. LADBS's website has a guide to what requires a permit, and a short call to the department settles a doubtful case. Working without a permit can lead to orders to stop, fines, trouble selling the property and difficulty with insurance, so check first.

Step one: check the zoning

Before drawings, look at the parcel on ZIMAS, the city's Zoning Information and Map Access System (zimas.lacity.org). It shows the zoning, the general plan land-use designation, overlays such as hillside or historic districts, and other rules that affect what you can build. Hillside areas have their own limits on size and grading. Historic districts can require review of exterior changes. Accessory dwelling units, the backyard homes and garage conversions that state law has encouraged, have their own rules; see Department of City Planning for the planning side.

If you are buying a property for a project, check these things before you close; Buying property in Los Angeles: taxes, ULA and the closing steps covers the purchase.

Step two: choose the type of review

LADBS handles permits in several ways, depending on the project.

  • Over the counter or express. Simple projects can be approved quickly, sometimes the same day, online or at a counter. The department's Restaurant and Small Business Express Program is one example of a faster track for qualifying work.
  • Plan check. Larger or more complex projects require plans to be reviewed by engineers and plan checkers. The reviewers check the drawings against the building code and other requirements, then return corrections. You make corrections and resubmit.
  • Other departments. Depending on the project, the Bureau of Engineering, the Fire Department, the Department of Water and Power, City Planning or the Bureau of Sanitation may need to sign off.

Step three: apply online

LADBS provides an online permitting system, accessed through permitla.lacitydbs.org, for many permit types. You create an account, enter the address and the project description, upload plans and documents and pay fees. The department's site lists what is accepted online and what still must be handled in person. Applicants who are not licensed contractors or architects should confirm what the law allows an owner to do. California requires contractors who do work above a dollar threshold to be licensed, and owner-builders take on responsibilities that the permit application explains.

What you generally need to submit:

  • A completed application with the address and parcel information.
  • Plans drawn to scale showing the existing and the proposed work, and for many projects, structural calculations and energy compliance documentation.
  • Documents from other departments where required.
  • Contractor and insurance information if a contractor will do the work.

Step four: plan check and corrections

For projects that go through plan check, a reviewer examines the plans and issues a correction list. You revise and resubmit. This round can repeat. The fastest way through is to submit complete, well-prepared drawings and to answer each correction directly. Professionals who file permits regularly know the department's expectations, which is a reason many homeowners hire an architect or an expediter for complex work.

Step five: pay the fees and get the permit

LADBS fees depend on the type and scale of the project, and there may be fees from other agencies, such as a school development fee, a sewer fee or a planning fee. The department's online fee calculator gives estimates, and the current fee schedule is set by ordinance. Fees are paid when the permit is issued, and the permit is then available for pickup or print online. Post the permit card at the site where inspectors can see it.

Step six: inspections

Permits are not the end. A permit only allows work to begin; inspectors verify that the work is done correctly. Inspections occur at stages, such as foundations before concrete is poured, framing before walls are closed, electrical and plumbing rough-ins, and a final inspection at the end. You request inspections through the department's online system or by phone, and an inspector visits the site, approves the work or lists corrections. Do not cover work that needs inspection until it passes. A project is complete only after final inspection, and for new buildings or a change of use the department issues a certificate of occupancy.

Permits expire if work does not begin or if it stops for an extended period, so keep an eye on the dates on the permit and ask the department about extensions before they lapse.

Special situations

  • Fire rebuilding. After the January 2025 fires, the city set up expedited programs for rebuilding homes lost in the Pacific Palisades; the department's site describes the current process for affected properties.
  • Earthquake safety. Older buildings with weak first stories, concrete buildings and other vulnerable types have retrofit requirements. LADBS publishes the program information.
  • Hillside and historic properties. Extra reviews apply.
  • Unpermitted work. Owners who discover old unpermitted work can apply to legalize it, which requires plans and inspections. The department can advise.
  • Code enforcement. If a neighbor or inspector reports a violation, LADBS can issue an order; correcting it generally requires a permit.

Business permits are different

If you plan to open a shop or restaurant, building permits are only one part of the picture. Starting a business in Los Angeles explains the business tax registration and other approvals.

Records and help

LADBS keeps permit records for each property, which are public. Looking up a property's permit history is a good step before buying or remodeling. The department's website has instructions for each permit type, and its offices answer questions. See Department of Building and Safety for the department's role and Department of Public Works for the related city departments.